December 12, 2025
Webuild: 15th caisson installed and more than 50,000 gravel columns completed
Supervising the depths: high-tech monitoring converts seabed into data
- The 15th caisson has been positioned and the milestone of 50,000 installed gravel columns surpassed, with 79% of the seabed foundation completed
- A dense network of sensors, including piezometres and inclinometres, monitors the ground under the breakwater at depths of up to 50 metres, transforming the invisible marine construction site into precise engineering data
- "The Breakwater’s Eyes": second episode of “Number Ten” web series goes online, exploring 10 points of excellence of New Genoa Breakwater built by PerGenova Breakwater consortium led by Webuild, the latest dedicated to sophisticated underwater geotechnical monitoring systems
GENOA, December 12, 2025 – The construction site of the , one of the most complex maritime works in Europe, is progressing both above and below the water’s surface. The PerGenova Breakwater Consortium, led by Webuild, has completed the installation of the 15th caisson, while more than 50,000 gravel columns having been set, equal to 79 percent of the total planned. Meantime, overall progress on the pouring of gravel on the seabed as part of the consolidation of the foundation has reached 87 percent. The project is being done on behalf of Western Ligurian Sea Port Authority.
Crucial progress on the foundations – although invisible, they form the backbone of the structure – has also involved the installation of drains, each 22 metres long, at a depth of 30 metres. They are essential to stabilise and level out the support base of a section of the breakwater.
One feature of this project is the constant supervision of the underwater construction site. Given the exceptional depths involved - up to 50 metres - the use of high-tech monitoring systems managed by third-party supplier SOCOTEC is essential.
As highlighted in the “” web series produced by the consortium, the monitoring activities are described as the “eyes of the breakwater” and compared to the work of a master tailor: an essential task in an area that must be constantly supervised, anticipated, and understood.
In order to ensure structural stability, a dense network of sophisticated sensors – including piezometres, inclinometres, and profilometres – has been installed to monitor the breakwater’s foundation. These interconnected instruments process real-time data on conditions like pressure and ground movement that can occur on the seabed. The data enable the creation of maps and models that support every engineering decision. In parallel, aboard the vessel “Implacabile”, technicians carry out readings 12 hours a day, seven days a week, ensuring that every phase of the project is carried out with maximum safety and precision.
Once completed, the New Genoa Breakwater, with its length of six kilometres, will allow the Port of Genoa to accommodate ships up to 400 metres long, making it a privileged hub for major international maritime routes. The project, part of an integrated infrastructure system with the Terzo Valico dei Giovi–Genoa Junction, also under development by Webuild, will strengthen connections between the Mediterranean and the heart of Europe.
Number Ten - Gli occhi della diga
Diga Foranea di Genova, posa cassone 15